Town News

Upcoming Road Work in Frisco and Travel Impacts

The Frisco Public Works Department and third-party contractors will be working on street resurfacing projects throughout the Town of Frisco starting on Monday, April 29 through Monday, May 20, 2024, weather dependent. These projects and related street closures will have an impact on traffic and will be signed several days prior. Residents are being asked to plan ahead, as these crews perform the necessary work, and Frisco Public Works thanks all residents and visitors for their patience, while this vital street work is completed.

Mill and Overlay on Town Streets

During a mill and overlay, the top layer of old asphalt is ground off, and tack oil is placed on the existing road to help bind the new asphalt. A new layer of asphalt is then applied, creating a roadway that is uniform in color, quality, and level.

Timing and Affected Areas

Milling will take place starting Monday, April 29 through Friday, May 3, 2024 from 7:00 am until 6:00 pm, Monday-Friday only. The overlay will be applied starting Monday, May 6 through Friday, May 10, 2024 from 7:00 am until 6:00 pm, Monday-Friday only. Stripping of West Main Street will be completed on Monday, May 20, 2024.

  • Creekside Drive from 4th Avenue Bridge to Miners Creek Road
  • Creekside Drive Bridge located near West Main Street
  • Little Chief Way
  • 5th Avenue from Granite Street to Bills Ranch Road
  • West Main Street from the Kayak Overnight Parking Lot to Creekside Drive
  • Miners Creek Road

Impacts

  • The bridge located on Creekside Drive near West Main Street will have a full closure with detours in place from 7:00 am – 6:00 pm, during the week of May 6, 2024
  • Little Chief Way, 5th Avenue, West Main Street, and Miners Creek Road will have flagging operations in place to allow for through traffic by keeping one lane open.
  • Weather and general conditions will determine the schedule which is why mill and overlay operations will be signed on specific streets shortly prior to the work being performed. Motorists in those areas are urged to look for those signed notifications.

Any questions related to the milling and paving may be directed to Town of Frisco Streets Department Supervisor, Landon Sengelman, at LandonS@TownOfFrisco.com or by calling the main Public Works phone line at 970-668-0836.

Frisco Mill and Overlay Map for work being conducted April 29-May 10, 2024